This week..

  • Flat conversion continues

Flat En-Suite

Just three days to work on the house this week (for me) so it is all focused on the Flat conversion. I finish building the stud walls and the plumber does the 1st fix (no pictures of his work - I will include them next week)

Next I build the bedroom/kitchen wall

1st the frame...

then the bracing

then the Fermacell

leaving the back open for the electrics & plumbing


Then a Wardrobe

I have designed this to use the cupboard doors from Mum's lounge (cut down) which have not warped.


BT's Home Highway ISDN Update

You will recall the on-going major dispute with BT (see Week 111 and all weeks since). It has been unusable since May.

Still no response this week.

To be continued.....


 

From the Archives....

So we don't forget what we have achieved here is a quick look at what we were doing one and two years ago.

Two years age ( Week 19 on the left) the 1st blocks of the main house are laid!

One year ago,  (Week 71 on the right) the new water main is connected

 


Next week:

  • The remaining 26 doors will be fitted!
  • Door furniture fitting & oiling

Next Week

 

Top of Page

We are now accepting B&B (with guided tours for self-builders)

visit www.baconandeggs.co.uk

Digital Cameras supplied by Olympus UK Limited

This site & its contents Copyright 2001-7  Imagekings Limited. All rights reserved.