Week130 - 5Apr 2004

This week..


Laundry Chute

The last task required for the NHBC final inspection was to make the laundry chute fireproof. Clearly in its current state it is a "chimney" from the basement to the 1st floor! The solution was Rockwool insulation and Masterboard fireproof board.

-
-
-
-
-
-

Decoration

Also this week the corridor upstairs gets it final coat of paint prior to final fix.

-
-
-
-

BT's Home Highway ISDN Update

You will recall the on-going major dispute with BT (see Week 111 and all weeks since). It has been unusable since May.

No progress this week. 

To be continued.....


From the Archives....

So we don't forget what we have achieved here is a quick look at what we were doing one and two years ago.

Two years ago ( Week 26 ) the bricklayers continued to make good progress - here my study takes shape and ....
One year ago, (Week 78 ) I move into the study!