A (4-day) week of little progress:

Little to show this week, disappointing but after 28 weeks, not bad! The weather was very bad Mon/Tue (Windy & wet) and the scaffolders let us down. We need more scaffolding & they say until they have dismantled another site they don't have any!!
Under-floor heating is a problem in this respect, we can not lay the floor boards until it is in. We can not put in until the roof is on hence we need internal scaffolding to allow the carpenters to finish the roof, to allow the tiles to water-proof the house to allow the under-floor heating etc etc!
Some minor extra brick/block work was required before the carpenters could finish fitting the trusses.

Next week: