Weeks 34 & 35 10 May 2002

Two weeks combined due to the Jubilee celebration and a football match......

Shane (Warner Roofing) trimming....
...and fitting the slates around the Velux windows
The roof over the Main bedroom complete
The whole-house ventilation is delivered - I will fit this.
The main stair window (Anderson Windows) is assembled...
...and fitted.
The windows are plastic coated outside & natural wood inside. The circular and semi-circular windows grills come pre-fitted, the remainder will have their exterior (white) grills and internal natural wood grills fitted later.
We build a temporary staircase. This is essential from a safety and practical viewpoint - there is so much to be carried upstairs.

Next Week