Week61 - 9Dec 2002

Progress this week

The terracotta tiles are delivered
For (both) kitchen floors

A replacement front door arrives. Same problem, 2 more on order! See Week 59 for the door saga!

The weather and therefore the house became so cold..
I decided to fit the hood....
and light the fire for the 1st time

The 1st to 2nd floor stairs are fitted
View from the 2nd floor

The steps to the garden are completed
The drive is cleared
The edge is back-filled
The ramp to the external door (required by building regs) is built

The heat pump is in place, wiring and pipework is connected.
One of five manifolds for the UFH

Next Week