Week70 - 10Feb 2003

Progress this week

Soil pipe boxed in...
with matching panelling supplied with the kitchen
Lights fitted under the units

These lights had a very short service life and we eventually replaced them with LEDs in 2015

The temporary handles and catches are removed..
and the permanent ones fitted.
Microwave etc moved in!
Kitchen door stained
Final outside lights fitted
Architrave & skirting staining..
and fitted.
Spindles fitted to 2nd floor landing/stairs